What are the steps of upgrading from Concept V2.5 to Concept V2.6?


 The best way to go about this is to export project files in 2.5 and then import them into 2.6
1-Upload State RAM
2-Save the project
3-Create the .asc file using the Converter Utility of Concept V2.5
4-Copy the.asc file into a new folder
5-Import the .asc file using the Converter Utility of Concept V2.6 SR7
6-Download executive into controller to support Concept V2.6 SR7
7-Download project into the controller (Include State RAM)

Upgrading from Concept V2.5 to V2.6 SR7 is illustrated in the attached upgrade file.