What are the initial tests that should be carried out when using the Masterpact NW for the first time? Should any primary or secondary injection tests be done?

All our breakers go through various testing procedures before leaving the factory, and it is not compulsory to conduct primary / secondary injection tests. It will be enough if the Customer sets the required parameters on the control units follows the procedures given on page 40 of the attached User Manual.